Fort Collins Project
Fort Collins, CO
Project #: 4-2025 | Commercial
Assignment: Maximize the redirection of material away from the landfill and minimize the incremental cost of deconstruction relative to “standard demolition”
Description: Complete demolition of one church and one office building
Duration: 8 months
Project Contact: Bob Tobiason
408-605-7179
bobt@circbuild.com
Comments: N/A
Project Metrics:
Materials categories diverted:
Metals
Millwork exterior
Millwork interior
Electrical
Furnishings
Specialties
Doors
Windows
Concrete
Analytics:
Objects Obtained: 253 objects (desks, chalk boards, lights, etc) diverted from Landfill and donated to local nonprofits
Volume of materials diverted from the landfill: 460 cubic yards
Reduced area in landfill: approx. 35’ x 35 x 10’
Recycled objects: 1.2 millions pounds of concrete recycled, 46,000 pounds of metals recycled
Energy saved: 42,025 kgCO2e diverted from the landfill, this is the equivalent of 105,000 miles driven in a gasoline car, 71 flights from Denver to New York, or 210 tree seedlings absorbing carbon for 20 years.
Jobs created: 556 labor hours